Operations Management and Factors Affecting Productivity (100 points)
Maduro Cleaning is a small organization that provides cleaning services to both residential and commercial clients. As a small organization, the owner assigns crews of two, three, or four employees to jobs each morning but the owner does not have a good method of determining a reasonable amount of time that each cleaning should take. The owner decided to keep data on job times and crew sizes in the hopes of developing a productivity measure.
Address the following requirements:
Crew Size Avg: Productivity per Crew
Directions:
Review the grading rubric to see how you will be graded for this assignment
BRIEF ANSWER AND EXPLANATION !!
Part a.
In order to find the crew size that hs the best productivity per worker; it is effective to divide the meters cleaned per day by the number of workers. Below is the mathematical Solution
2-man Crew Productivity = 3765 / 2 = 1,882.50
3-man Crew Productivity = 4915 / 3 = 1,638.33
4-man Crew Productivity = 6309 / 4 = 1,577.25
From the solutions above the 2-man crew is the most productive. This team size maximizes the output per individual.
Part b.
Based on the results, it is likely that crews larger than 2 impede productivity, because the workers are getting in each other’s way. Additionally, larger crews may exhibit a higher degree of socializing, which could detract from performance.
Part c.
By increasing from 2 to 3 men, productivity declines by 12.97% (1,638.33/1,882.50 – 1 = .1297). By increasing from 3 to 4 men, productivity declines by 3.73% (1,577.25/1,638.33 – 1 = .0373). The decline in productivity seems to diminish as the crew count gets bigger, but this doesn’t seem logical. Perhaps, there are other underlying drivers at play. Since we lack a larger data set to study, let us take the average of the two productivity decline percentages as follows: (12.97% + 3.73%)/2 = 8.35%.
Using this data point, the projected productivity for a 5-man crew is below.
5-man Crew Productivity = 1,577.25 * (1 – .0835) = 1,445.55